Exhibiting Guide

When should you appoint an exhibition stand builder?

Appoint your exhibition stand builder as soon as you know your stand is more than a basic shell scheme, well before the organiser's own deadlines are close. Exhibitor manuals set drawing approval, RAMS and insurance deadlines weeks before the show opens: London Tech Week 2026 asked for rigging and health & safety paperwork by 15 May for an 8-10 June show, and graphics and furniture a week before that. A plot the size of our 450 m² space-only pavilion for 55 companies at that show needs every one of those weeks to clear the manual before the hall opens.

Tell us your show and date →

Published 28 October 2026

Built To The Manual

Where this came from: a 450 m² pavilion built straight to the manual's deadlines

The Turkish national pavilion at London Tech Week 2026, 450 m² and 55 companies under one DUM FLEX™ structure for the Government of Türkiye, had to clear the show's drawing, RAMS and insurance deadlines as one structural submission. That only works if the builder is already on board, with a design settled, well before the manual's clock starts running.

The Calendar

Work back from the organiser's deadlines, not the show date

Every exhibitor manual we have worked to publishes its own run of deadlines, and they sit weeks before the show opens.

Two real manuals, two different gaps

London Tech Week's 2026 Standbuild Guidelines put graphics and furniture submissions at 8 May, rigging and the health & safety form at 15 May, freight at 18 May and AV at 25 May, against an 8-10 June show — the earliest of those lands roughly four and a half weeks out, the rigging and H&S paperwork about three and a half. Advanced Engineering's 2026 manual sets its space-only plan, RAMS and insurance submission for 21 September against a 4-5 November show, close to six weeks out. Neither gap leaves room to start designing after the deadline has already passed.

What has to be finished before that date, not after it

The deadline is when the drawing pack, RAMS and insurance certificate are due. The stand still has to be designed and settled well ahead of that date. By that date you need a settled layout and a structure an organiser will actually approve for that hall.

Why a late appointment collapses two jobs into one

Appointing a builder the week the deadline lands means the design conversation and the approval submission are happening at once, with no room to fix what the organiser sends back. A builder who already knows the manual can submit a complete pack first time; one starting from a blank brief that same week cannot.

Turkish national pavilion, London Tech Week, Olympia London
London Tech Week, Olympia London
Complex Builds

A double-deck structure or a multi-company pavilion needs more runway

Size and structure move the appointment date earlier than the manual's own deadline suggests, because the design itself takes longer to settle before it can even go to the organiser.

Structural sign-off adds a step before the deadline

A double-deck stand, like our 55 m² build for Turkish Technic at MRO Europe or the 270 m² double-decker pavilion we built for Emlak Konut at Cityscape Global, needs engineer-calculated structural drawings inside the same submission as a standard stand's RAMS and insurance. That calculation work has to finish and be reviewed internally before anything goes to the organiser, which pushes the point where a builder needs to already be appointed and designing well ahead of the manual's own cut-off. Our RAMS guide covers where that structural threshold sits.

A pavilion multiplies the approval, not just the floor area

A 450 m² pavilion with 55 companies dressing their own bays inside one structure is not one approval, it is one structural submission plus a sequencing plan for every company working inside it. Getting that right against a fixed date, rather than going back and forth with the organiser once the clock is already running, is why a pavilion at that scale needs its builder settled well before a single stand would.

Starting Late

What a late start actually costs you

Appointing a builder after the organiser's early deadlines have passed does not stop a stand getting built; it changes who is setting the schedule.

Once the manual's drawing or RAMS deadline has gone, the design brief stops being yours and starts being whatever fits the time left before the next hard cut-off: freight, AV, or the show itself. Material choices narrow to what a workshop can turn around fastest, structural options that would have needed engineer sign-off drop out because there is no longer time for a resubmission, and any back-and-forth with the organiser over a rejected drawing eats into build time rather than design time. None of that is a reason to panic a late enquiry away — we can usually still get a shell-scheme or straightforward space-only stand through on a shorter run — but a double-deck structure or a multi-company pavilion needs the full runway in this guide.

From Day One

What we do from the day we are appointed

The organiser's manual becomes the project's spine from the week we are brought on.

The manual first, the design second

We ask for the current exhibitor manual and the hall or venue's own technical pack before the design brief is finished, because the structure, rigging limits and approval route for that specific hall shape what we can design. Every deadline in the manual, drawings, RAMS, insurance, freight, AV, goes on the project calendar against the show date in the first week, so nothing is discovered close to a cut-off.

Design run on the deadline that actually matters

The design has to be finished and approvable by the organiser's drawing and RAMS submission date, which sits well ahead of the show date itself. We design, review and submit to that date with room for one round of organiser feedback, rather than discovering a problem with the structure the week before build-up.

Send us your show and manual →
Questions

When to appoint a stand builder: the questions we get asked

How early should I appoint an exhibition stand builder?

As soon as you know your stand is more than a basic shell scheme. Organiser manuals set drawing, RAMS and insurance deadlines weeks before the show, typically three to six weeks depending on the show and the stand's complexity, and a double-deck structure or multi-company pavilion needs longer again for structural sign-off. Appoint while there is still time to design and submit, well before that deadline is close.

What are the key factors in choosing an exhibition stand builder?

Evidence of similar work at the scale and complexity you need, familiarity with the specific venue or organiser's manual, and in-house design and production rather than a brief handed on to a third party. For a space-only or double-deck build, experience getting structural drawings through that organiser's approval process matters as much as the design itself.

Does the appointment date change for a shell-scheme stand?

Yes. A basic shell-scheme stand, walls and fascia the organiser already built, carries a far shorter manual process, usually just graphics and furniture artwork, so it can be appointed closer to the show than a space-only or double-deck build. Our shell scheme vs space only guide covers which category a stand falls into.

What happens if I appoint a builder late?

A straightforward shell-scheme or space-only stand can usually still be built on a shorter run. What changes is control: the design brief narrows to what fits the time left before the next hard deadline, and anything needing structural sign-off or a resubmitted drawing has less room to recover if the organiser sends it back.

Does a multi-company pavilion need an earlier appointment than a single stand?

Yes. A pavilion is one structural submission plus a sequencing plan for every company working inside it, which takes longer to settle before it can go to the organiser than a single stand's drawing pack. Our 450 m² pavilion for the Government of Türkiye at London Tech Week 2026 is that scale of submission.